Building Envelope Construction Sequence (title slide)

11/16/2001

Click here to start

Table of Contents

Building Envelope Construction Sequence (title slide)

Foundation & Lower Level Interior Walls

Recessed Rim Joist @ Main Level

2” Rigid Insulation @ Upper Rim Joist

Recycled Post w/ Glulam Beams

Main Floor Interior Structure

Recycled Posts & Glulam Beams

Perimeter Stud Wall @ Foundation Wall

Insulated Perimeter Stud Wall @ Foundation

Blown-In-Blanket (BIBS) Insulation

Lessco Vapor Barrier Box @ Interior Strapping

Lessco Vapor Barrier Box & Taped Vapor Barrier

Sealed & Taped Tu-Tuff Vapor Barrier

Interior Horizontal Strapping & V.B. Detail

V.B. Detail @ Partition/Exterior Wall Strapping

Interior Strapping/Drop Rafter/V.B. Detail

Loft/Drop Rafter/Window V.B. Detail

Exterior Rain-Screen Furring & Tyvek Housewrap

Author: Thomas Brown

Email: tbjs@coredcs.com

Home Page: http://www.tombrownarchitect.com

Other information:
A complete slide or PowerPoint presentation, with many additional construction and completed views, is available by contacting Tom Brown.

RETURN TO CASE STUDY MAIN PAGE